Demolition Now in Process at Midland Avenue

Demolition work at the existing Archdiocesan Center Building on Midland Avenue in Paramus is in progress and on schedule. The interior of the five floor building is being demolished and being prepared for renovation to accommodate the new Archdiocesan Center. According to Biniamin Malki, Archdiocesan representative on site, the fourth and fifth floors are completely demolished and the remaining floors will require a week each with the exception of the first floor which will take approximately three weeks. Mr. Malki said, “Barring any unforeseen issues, we should be ready for the renovation to begin by the end of November.” The demolition work is being carried out by Hanna’s Construction.